Contract between Brentford Dock Ltd and Pinnacle PSG

 

The board of Brentford Dock Ltd - which is supposed to represent its shareholders - refuses to allow its shareholders to have a copy of the contract between Brentford Dock Ltd and Pinnacle PSG.  It "allows" shareholders to view the contract in the Management Office between 8.00 am to 5.00 pm Monday to Friday.  Shareholders are not permitted to photocopy any part of the contract but can make as many notes as they like.  There is no facility for those who work during the day to view the contract.

 

Shareholders are paying for this contract (through their service charge) and are not allowed to have a copy of it.  Shareholders (service-charge-payers) do not know what is in the contract.  No summary or any other document has been circulated nor has there been any discussion of the contract.

 

Key Points of Contract

The main body of the contract is 63 pages long, split into 9 sections. In addition various schedules are attached to the contract.

It came into force on 1 June 2002 and is for the 3 years ending 31 May 2005. It can be terminated earlier by either Pinnacle or BDL, subject to various conditions being met, by giving written notice of at least 6 months.

BDL can further extend the contract by up to 2 contract years subject to giving suitable advanced warning prior to the end of the current period (31 May 2005).

This contract replaces anything that was previously agreed between Pinnacle and BDL.

There is a "non exclusivity" clause in the contract meaning that the Board of Directors can at anytime carry out any part of the services themselves or ask at third party to do so.

BDL can propose "major or substantial"  changes to the contract and Pinnacle can adjust the price accordingly.

Pinnacle can propose "major or substantial" changes and BDL can evaluate them in full. BDL can modify, accept or reject Pinnacle's proposals without giving reasons.

The contract requires Pinnacle to develop a procedure for dealing with any claims, complaints or enquiries received in relation to this contract and their responses. This record is available to any Director on request.

The Board of Directors and Pinnacle will meet quarterly to review performance of the contract by Pinnacle.

A comprehensive record of reports of service 'failures' is also kept

Signed by John Swinney (Pinnacle PSG) and Charmian Allcock (Chairman, Brentford Dock Limited) and dated May 2002

Includes sections on Quality Systems, People (Pinnacle are accredited with Investor in People Status) and Health and Safety

 

Pinnacle's Responsibilities and Performance Standards

Pinnacle are required to perform the service to the "Contract Standard" which requires them to use all "due skill, care and diligence, comprehensively and strictly - in accordance, and in compliance, with:

The key performance requirements [see below] for the Service,

All other provisions of the Contract Documents

Any local guidelines, in particular (but without limitation to) those relating to customer care, and any other such guidelines as may have been put forward to, and accepted in writing by, the Board of Directors.

The reasonable instructions issued to Pinnacle by any Authorised Director, pursuant to or in connection with the contract,

All legislation

 

And shall do so:

In an efficient, professional and courteous manner

In a manner which shall preserve, promote and enhance and shall not prejudice the reputation and interests of Brentford Dock Limited,

In good and full co-operation with Fellow Contractors; and;

In an efficient, professional and courteous manner

In a manner which shall preserve, promote and enhance and shall not prejudice the reputation and interests of Brentford Dock Limited,

In a manner, which secures to the highest standards, the interests and welfare of the residents and the management and maintenance of the Property."

 

"Pinnacle PSG shall employ sufficient fully and suitably trained, briefed, qualified and experienced staff to ensure that the service is, throughout the Contract Period, provided in all respects to the Contract Standard".

Pinnacle will also train staff, where appropriate.

 

A performance default applies to any failure by Pinnacle to perform the service properly. The contract states, "It is understood and accepted by Pinnacle PSG that the overriding objective of this contract is to ensure that the service is provided such as to ensure that the Property [Brentford Dock] is managed and maintained to the highest standard."

 

The contract also includes provision for dispute resolution.

 

Service Delivery Plan

The contract includes a 'draft' Service Delivery Plan covering the Period June 2002 to May 2003. Key areas of activity include:

Resident's Handbook (draft stated it was due for issue in the first week in June 2002)

Lease Extension Programme

Dock Road - Secure improved management of this area, ensuring vehicular access is limited in accordance with legal entitlement and that proper measures - including enforcement of any weight restrictions - are taken to protect damage to the surface

Parking Review - Pinnacle PSG shall use its best endeavours in conjunction with the BDL Board. Consultation with shareholders will form an important part of this review.

Five-year programme of estate works. Proposals by August 2002 - provides for subsequent consultation with shareholders

BD Leisure Services - full option appraisal of the Marina Club Operation for report to the BDL Board no later than August 2002.

BD Enquiry System - full implementation of computerised BD enquiry system covering property, leaseholders, vehicle and works interrogation facilities - no later than 30 September 2002

Website Development - provide advice and assistance to BDL

Space Audit - By Nov 2002 - maximise space utilisation and income opportunities

Strategic Direction - Work with Chairman and Board to maintain and improve environment and capital value of properties.

 

Contract Price

Comprised of 4 elements:

1

Annual Sum

2

Hourly and Weekly rates

3

Any % Fees

4

Bond Premium

 

It is believed the £618,003 in the table below covers 1 and 3 above. There was no total of Bond Premium in the copy of the Contract shown. Hourly and weekly rates apply as they are incurred (so obviously not included in figure below).

 

Pinnacle Fee for Year Ended 6 April, 2003

     

Pinnacle fee £

 

Estate Services

     
 

Wages and contact labour

36,238

 

2 x handy persons

 

Gardening

31,450

 

2 x gardeners

 

Estate Services

104,250

 

6.5 x cleaners inc. road sweepers

 

Security

73,288

 

2 x out of hours staff, call centre and contract security

 

Management & Supervisory

120,774

 

 

 

Other Estate Services

25,000

 

 

 

Repairs and Maintenance

30,000

 

 

Total Estate Services

 

421,000

 

Admin Costs

 

 

 

 

Office Costs

24,000

 

 

 

Accountancy

42,000

 

 

Total Admin Costs

 

66,000


 

Total Service Charge

 

487,000

 

Profit 8%

 

38,960


 

   

£525,960

 

+ VAT 17.5%

 

92,043


 

TOTAL

 

£618,003

 

 

 

Annual Performance Review

The contract includes the provision that an annual performance review will be undertaken.

Analysis of service through previous year

Successful service areas outlined and areas where improvement is required are also outlined

The reasons for success / failure identified

Comparison of service benchmarked against other Pinnacle clients

Risks, associated with provision of the service, detailed

Action plan setting out measures to be taken to improve service where appropriate.

 

Between the 2nd and 3rd anniversaries of the contract starting BDL can carry out a thorough 'value for money review' of the contract and BDL can terminate, with 6 months notice, if they don't believe the contract is offering value for money.

 

Performance Standards

This is a complete list of all the targets Pinnacle are working towards:

Indicator

Definition

Performance Target

Service Improvement Target

Income Collection

% of service charge due which is collected by end of financial year

Collection to accord with local guidelines. %s to be measured against a residual debt figure of 3%

Yr 1 = 99.5%

Yr 2 = 100.5%

Yr 3 = 100%

Yr 4 = 100%

Yr 5 = 100%

Customer Service (8.00am - 5.00pm
Monday to Friday)

Telephone Answering

Within 6 rings

 

Letters & emails - time for a substantive response

Within 6 working days

Yr 1 - 2 = 6 working days

Yr 3 - 5 = 5 working days

Out of Hours

Telephone Answering Response Rate

Within 6 rings

 

Out of Hours Attendance

Within 6 rings

 

Patrolling

Minimum 6 patrols per 12 hour shift

 

Key holding / Parcel Delivery Service

As and when required

 

Estate Services

Graffiti Removal

Within 1 working day

 

Clearance of waste bins

As & when half full but in any case no less than 3x per week

 

Cleaning (Estate & Blocks)

All weekly tasks to be completed in accordance with mutually agreed local guidelines

 

Bulk Refuse Removal

within 1 working day

 

Abandoned Vehicles

Report to LBOH within 1 working day

 

Parking Enforcement

Issue of notice within 2 hours

 

Gardening

Grass Cutting: When or before 7cms

The following in accordance with mutually agreed local guidelines:

" Turfing / seeding

" Management of banks & boundaries

" Pruning & mulching of shrub beds

" Implementation of tree programme

 

Repairs

 

 

Completion Rate as a % of in-flat repairs within specified target time

Urgent = 1 day

Non-Urgent = 3 days

Yr 1 = 80

Yr 2 = 85

Yr 3 = 90

Yr 4 = 90

Yr 5 = 90

Completion Rate as a % of estate repairs within specified target time

Urgent = 1 day

Non-Urgent = 3 days

Yr 1 = 85

Yr 2 = 90

Yr 3 = 95

Yr 4 = 95

Yr 5 = 95

Replacement Bulbs

Within 1 working day of report

 

Communications

 

 

Dock Newsletter (all shareholders and residents)

No less than 1 / month

 

Shareholder / Resident Meetings Attendance

up to 3 x per year (each block) and 2 x year (estate)

 

Block Inspection

Monthly

 

Brentford Dock Enquiry System

Implementation & Maintenance

All info to be backed up as agreed from time to time

 

Board Information

Management Reports to Board

Except by agreement with the Chairman, no less than 48 hours in advance of meeting.

 

Accountancy

Management Accounts

To relevant Board within 15 working days of quarter end

 

Annual Draft Service Charge Budget

As per instruction from BDL Board, to include a monthly profile of anticipated income & expenditure

 

Spending Authorisations & Banking Arrangements

As agreed from time to time and appearing in agreed local guidelines but always subject to prior Board approval for any spend outside the scope of the annual contract sum

 

Cashflow

Monthly statement of cash at bank and projected movement over coming month to relevant Board

 

Monthly listing of creditors and debtors to level of detail requested from time to time to relevant Board

 

Remote access to information

In accordance with local guidelines

 

 